Construction Updates


  • Public Utility Relocation Work 06/06/16 - 10/13/16

  • Demolition (temporary local sidewalk barricades) 07/12/16 - 10/07/16

  • Excavation/Deep Foundations 10/10/16 - Mid-December 2016

  • Start Sidewalk/ Lane Closures 11/07/16 - Spring 2018
    (South side of Addison and East side of Clark)

    1. Clark Street
      1. Canopy over sidewalk starts 11/08/16 - 12/01/17
      2. Lane closure will begin 11/08/16 - 12/01/17

    2. Addison Street
      1. Canopy over sidewalk starts 11/10/16 - 12/01/17
      2. Lane closure will begin 11/10/16 - 12/01/17


  • Construction 11/07/16 - 06/30/18

*Dates subject to change due to weather conditions and scheduling.